We participated successfully in Elering AS substations maintenance procurement for next four years. Although the area covered by contract is the same, i.e. Eastern regions of Estonia, the object of the contract was expanded which required us to find new partners.

We finished substantial two-year electrical work contract with UPM Kymmene Otepää AS by time. As a subcontractor of Siemens OY Eesti we finished the reconstruction of 110/15/6 kV part of the Puhja substation.